Thursday, February 25, 2010

Trains, HOT Lanes, Ferries and Tunnels: Honolulu Has Many Alternatives and Very Few Billions

I was very pleased to accept an invitation to speak at one of the nation's best public colleges, the University of California at Los Angeles (UCLA.) My presentation to their prestigious School of Public Affairs was on Trains, HOT Lanes, Ferries and Tunnels: Honolulu Has Many Alternatives and Very Few Billions.

The hour-long presentation was well received and the audience was surprised that such a disproportionally large and expensive system is planned for our city. They were disappointed that a huge amount of public funds are being spent for a project with low benefits. They were rather astounded by the apathy of the public in accepting such a megaproject for our small island.

The audience of professors and students in urban planning and public policy were generally in favor of transit, but transit needs to be selected and sized properly. The proposed transit for Honolulu fails any proportionality comparison. Projects like Honolulu's and San Juan's (heavy rail in island communities) give transit projects a bad name.

It is no coincidence that the same consultant (Parsons Brinkerhoff), for the same city (Honolulu) with a difference of six years (2000 versus 2006) concluded that a Bus Rapid Transit system will be far cheaper and will generate a higher transit ridership than rail. To avoid this comparison, BRT was not included in the 2006 Alternatives Analysis where rail was proclaimed the Locally Preferred Alternative.

The same analysis dismissed Light Rail and the Pearl Harbor Tunnel withing a few introductory paragraphs with no analysis whatsoever. HOT lanes were designed as a silly pipeline with no on- and off-ramps. Worse yet, they added 2 lanes and they took away the zipper lane, for a net gain of one lane. That one lane alone was only a hair inferior to the rail that was selected as the "winner."

HOT lanes is natural partner for BRT and Express Buses. Reversible HOT Lanes like Tampa's should be priority number one for our Waianae/Kapolei/Ewa/Mililani traffic to/from town. It is only about 10-miles from the H-1 and H-2 merge to downtown. Recall that in 2007 Tampa completed 10 miles of 3-lane reversible elevated road for a total of $320 million. Mufi Hannemann will spend over $300 million for rail paperwork and promotion alone. About $50 million from the feds. All the rest from our pockets. For paperwork, and smoke-and-mirrors shows and commercials.

======================================================
  • I only spent 24 hours in LA but it was a treat to cross paths and shake hands with past Massachusetts governor, presidential candidate, UH lecturer and now UCLA professor Michael Dukakis.
  • Air traffic shows that the economy has not recovered. LAX was rather uncrowded, inside the airport and outside on the roads. My return flight to Honolulu was less than two thirds full.
  • Traffic lights work very well in Los Angeles thanks to their advanced management center (ATSAC) and smart allocation of lanes for left and right turns. All major boulevards were flowing uncongested in the middle of the pau hana rush hour!

Friday, February 19, 2010

Who is Dependent on Cars? Mass Transit!

Ed Braddy of New Geography provides some clear explanations that without cars mass transit goes broke!

The quote below provides a quick summary, but the full article is very informative.

Yet in pursuing this transit-friendly future political leaders rarely confront this inescapable reality: public transportation is fiscally unsustainable and utterly dependent on the very car-drivers transit boosters so often excoriate. For example, a major source of funding for transit comes from taxes paid by motorists, which include principally fuel taxes but also sales taxes, registration fees and transportation grants. The amount of tax diversion varies from place to place, but whether the metro region is small or large the subsidies are significant.

Read it here: Who is Dependent on Cars? Mass Transit!

The passage below is a reality comparison between roads and transit--what is fiscally sustainable and what is not:

Many policy makers fail to focus on developing a fiscally sustainable plan for public transit. They miss the fundamental problem that anything heavily subsidized –particularly in a period of budget cuts– is unsustainable. Roads are subsidized at about a half-penny per passenger mile; transit subsidies are 100 times higher.

Wednesday, February 17, 2010

Panos Prevedouros on the Rick Hamada Program

For nearly three years now and on 40 or so Mondays per year I join political columnist and radio host Richard Hamada, III on KHVH 830 AM The Rick Hamada Program for a humorous, interesting and if I may say so, insightful, discussion on Honolulu city's issues and challenges relating to traffic and infrastructure, as well as on cost-effective ideas to mitigate these problems.

Here is a sample of the first four shows in 2010. Visit HonoluluTownPodcast.Com for more, including the "dark side", that is, Mayor Mufi's rail propaganda on the Mike Buck Show on KHVH.

They lied about the ridership, they lied about the costs, so why wouldn’t they lie about the jobs?

Randall O'Toole's blog provides this sobering insight in Rail Jobs Overestimated.

Randall also predicted Honolulu's likely predicament with rail by analyzing the extension of a heavy rail line in Washington, D.C. in $6 Billion Down the Drain

The interesting thing is that the motivation and conclusion are the same for Washington and Honolulu!
So taxpayers are on the hook for spending at least $5.2 billion — more likely $6 billion or more — for a rail line designed solely to benefit a few property owners and developers. But, as it turns out, even they won’t benefit from it.

Because rail is the 5% solution... 5% will use it, the remainder 95% will be stuck in horrendous congestion. And with more potholes and lane closures from water main breaks because the city's budget will be broke.

Is that a legacy worth leaving to our children?

Monday, February 15, 2010

Honolulu Rail's Cost, Route and Ridership Opinions

President's Day 2010 brought a lot of interesting perspectives on the table for Honolulu's $5.3 billion proposed elevated rail line. None of them favorable.

Dr. Kioni Dudley of Makakilo offers his perspective about the proposed rail in the Honolulu Star Bulletin. These sentences from his article are particularly insightful:
  • This rail is not being built to solve current traffic problems. It actually is not even for us. It is being built to benefit developers.
  • The traffic problems it will solve are future problems, yet to be caused by people yet to move into homes yet to be built.
Cliff Slater of HonoluluTRaffic.com covers the costs of the proposed rail in his article published in the Honolulu Advertiser. "The city's rail project is not merely the largest public works project in Hawai'i. It will be the fourth most expensive of any post-1950 metro area rail system in the nation, exceeded only by Washington, San Francisco and Los Angeles."

The article is great, but why should anyone read past its opening paragraph? Stop the insanity! should be the response. The fourth most expensive system in the US, proposed for an island paradise in the middle of the Pacific, with less than one million people. The governor should stop this grave error and refuse any approvals for it.

Finally Shawn Hao of the Honolulu Advertiser uses soft language but reveals other parts of the insanity in yet another well-researched article.
  • The benefit of the proposed rail: "Honolulu's planned rail line from East Kapolei to Ala Moana is expected to boost public transit use by about 1 percentage point by offering faster, more reliable service than buses." [Would you pay five billion to receive a 1% reduction? Follow Mufi and you will.]
  • The dropping ridership of TheBus. [I have plotted the statistics that Hao quotes from the Hawaii Data Book below. Transit ridership is on a steady downhill. But we keep buying more buses...]
  • The City's attitude: "We don't care what the Mainland is doing," Honolulu Transportation Director Wayne Yoshioka said.
Ainokea is right Mr. Yioshioka.

For the record, I see the numbers and Aikea.

Tuesday, February 9, 2010

Tuesday, February 2, 2010

FTA Will Pay for Honolulu's Rail... Maybe 25% of Cost ... in 2011

FTA commits $1.55 billion to pay for Honolulu rail system says today's breaking news (http://www.honoluluadvertiser.com/article/20100202/BREAKING01/100202030/F).

That sounds like such good news for Hannemann but it is not. The article says that IF all environmental reviews complete successfully, then FTA may be able to release construction money on or after September 30, 2011.

Note that there is no word on possible lawsuits against the FTA and the delays that they will cause. HonoluluTraffic.com sued the FTA in 2002 and achieved the impossible: FTA pulled the plug by rescinding the Record on Decision for Mayor Harris' Bus Rapid Transit proposal.


Also if you try to read between the lines, you will discover these two gems of truth:
  • "But please know that the FTA also takes an independent look at the finances of this project and we will do so again when they submit a financial plan to get into final design."
  • Groundbreaking on the elevated commuter rail was supposed to take place in December, but has been indefinitely delayed by an ongoing federal review...
Now this "good news" came out today from the President's budget which will be taken apart by Congress in the coming months, much like his health care bill. The funding for Mufi's rail may survive, or may not. This is a "make work" bridge-to-nowhere project and the fiscal outlook for it is bleak.

The guestimate I made yesterday that this project may start on 12/12/12 stands!

And in case you did not notice, the FTA subsidy will cover roughly only 25% of the budgeted cost, but with minor cost overruns the cost to the local taxpayer will be $4.5 billion, or $4,500 million. Furthermore, the imported rail equipment will cost more than the FTA contribution. So all of the FTA money will go to mainland, Canada, German or Korean suppliers. No FTA money will reach Oahu.

Monday, February 1, 2010

Rail Jobs? Apply Now for 12/12/12

Let's talk about the much touted "rail jobs."

Although public project construction jobs are only a small part of Oahu's economy, politicians and some union heads are literally shouting that we need the rail for the jobs that it provides to save Oahu from its economic slump.

First, much more than half of the planning and design work for the rail is done by outside professionals. Local engineers do not know how to do rail. Second, Kiewit Corporation of Omaha, Nebraska was selected to build the first segment (if and when construction can start legally.) Third, a lot of the technical work for rail requires expertise that our local laborers do not have. Fourth, a big part of the rail is the imported technology which will be shipped in and then assembled by outside experts. For these and other reasons the local jobs number will be much smaller than what politicians announce for popular consumption.

The next question is timing. Mufi and rail advocates are (again) shouting that jobs are needed now and rail should start now. Can rail construction start now? The answer is No. Here is why.

The Programmatic Agreement (PA) under Section 106 that addresses cultural and historical impacts has not been signed by all parties.

Regarding the PA process I heard this: "Faith Miyamoto representing the city has been picky as to which party to involve and has told affected parties that they are not participants in the PA." Actions like this endanger the conclusion of the PA process.

The Final EIS cannot be released before the PA concludes satisfactorily.

The judges of the federal court along Halekauwila Street do not want trains going by their building, yet no realignment has been proposed.

The Federal Aviation Administration is concerned that the transit corridor is too close to active runways that process millions of passengers every year. An alternative alignment would be required to satisfy their concerns but the city has not provided a realignment.

Let's now make a big assumption that concerns like the above, plus concerns about the budget are sorted out within months. Then these are the steps that city needs to complete:

1) Issue a Final EIS (with acceptable solutions to all major concerns)
2) Final review by the affected State Departments
3) Approval by the Governor
4) Review by the FTA and approval
5) FTA issuance of a Record on Decision
6) FTA issuance of a Letter of No Prejudice
7) FTA provides first installment of federal funds (Full Funding Grant Agreement)

The above process requires one full year to conclude (assuming that Governor Lingle will eventually approve the FEIS) and over two years to receive construction funds from the federal government. Of course a reckless mayor can start construction with no agreement with the FTA and realize later that FTA can deliver much less than what's in the budget.

The lesson here is that if you like rail, for the sake of your finances and of the generations to come, do not elect a mayor who does not promise that rail work will start after the full funding grant agreement has been signed by the feds. Hannemann wants to start with no federal funds.

Hannemann is wrong on at least four counts:
(1) He proposes rail as a traffic solution. Wrong.
(2) He proposes to build rail in a very expensive way. All-elevated heavy rail. Wrong.
(3) He plans to start rail in the middle of prime agricultural land. Wrong.
(4) He plans to start construction without federal funds. Wrong.

Meanwhile, as of January 2010, President Obama has frozen the spending of all departments due to the immense federal deficit. At the same time, there is no budget allocation anywhere for Honolulu's transit. Actually finding big money for it will be much harder than the local political rhetoric indicates.

The above schedule does not take into account delays from lawsuits. At least one lawsuit has been promised. Other federal departments may object to FTA's approval, thus more delays and injunctions are possible.

It does not matter what Hannemann or any politician or city representative says. Without completing the steps required by federal law, there will be no approval and no construction or on-the-ground preparation for construction.

I have a guestimate of a start date for those who remain optimistic about Mufi's rail actually going into construction: 12/12/12. That's less than three years away and about normal for projects of this nature and size.

How can we summarize the original question about jobs and rail? Too little too late.

Monday, January 25, 2010

Panos for Mayor... subject to incumbent's departure

Today, on the Rick Hamada show, I announced my intent to become a candidate for mayor of the City and County of Honolulu when the office becomes vacant.

As you know, the regular election for mayor is not until 2012 but Mufi Hannemann has declared an interest in the race for Governor. However, unlike U.S. Representative Neil Abercrombie who declared his intent to resign, Mayor Hannemann has not declared any such intent, thus today I am simply saying that if he resigns then I will run for mayor.

Our campaign’s committee of advisors has remained active since the 2008 elections and so did our website and campaign filings with the office of elections. Our new website is FixOahuNow.com and our campaign phone number is 63-PANOS. However, the phone line won’t be live until a formal campaign starts. On the other hand, the “contribute” button of the website is open for business!

I have lived on Oahu for 20 years and the condition of the public infrastructure has deteriorated to the point that we are ranked among the worst in the nation in traffic congestion and road quality. The city lost its lawsuit against the EPA so we now have a billion dollar obligation for secondary sewer treatment. None of it is being done.

Instead of addressing the trash problem, the city extended the life of the landfill and sued the company that can export our trash. Water main breaks are almost a daily occurrence with paralysis in Waikiki and Nanakuli recently.

There is little planning for resilience. What happens when a hurricane or a tsunami hits? What’s the plan for residents and for 100,000 frantic tourists?

There is a slate of four pro-rail candidates for mayor and a few more may join. However, I am more certain than ever that the proposed elevated rail is unsightly, unaffordable and unnecessary. In the 2008 vote, millions of dollars of false advertising were spent to deceive Oahu voters that the city was planning an affordable light rail system. However, all along the city was planning for an expensive, fully elevated heavy rail system.

When Bishop Estate and the architects of Hawaii voiced strong support for a partial light rail system, the city admitted that light rail was dismissed early in the process without much analysis. Also the Oahu Railway which is largely intact from Waianae to the airport was ignored. The inescapable conclusion is that the proposed rail is not about transit service. It’s about land development and expensive construction.

In a letter to the editor, mayor Hannemann promised a $3 billion rail system and fiscal restraints. (Read it at http://the.honoluluadvertiser.com/article/2006/Aug/19/op/FP608190324.html).

Despite his wishful thinking, no private monies were realized and the rail’s budget ballooned from under $3 billion to over $5 billion. Based on past experience, the actual cost will be over $6 billion. And it does not serve UH or Waikiki. And tax collections are low.

So the city plans to steal over $300 million from TheBus capital budget to balance the rail financial plan! We simply do not have the money for this system. If it’s built, then it will undermine our ability to issue bonds in order to pay for vital road, water, sewer and maintenance projects, as well as for bus operations and maintenance.

We need to focus on the economy, jobs and taxes. The only way the city can help is by focusing on its infrastructure and services. As mayor I will scrap the rail and replace it with real solutions and necessary maintenance. It is not acceptable that beautiful Oahu is a prime example of congestion, dilapidation and substandard infrastructure.

Sunday, January 24, 2010

Reality vs Livability

Which new word Mufi will bring us from Washington, DC? LIVABILITY.

This time it is not Mufi's fault. It's President Obama's through the mouth of his transportation secretary (and past pork meister) Ray LaHood.

Obama promised that large projects won't be done based on political whim and strong arming. He promised transparency, accountability and (indirectly) cost-effectiveness. In other words, only good, necessary and justifiable projects with strong local support and big bang for the buck will be done. Now he does exactly the opposite when it comes to urban rail systems.

All rail systems are money losers in the U.S. Before Obama there was a formulaic determination at Federal Transit Administration so that the taxpayer won't be taken on a wild ride by spending hundreds of millions of dollars on projects that are grossly ineffective. Honolulu's systems is grossly ineffective because it costs over three times more that the next most expensive system in the nation, and about 20 times more the typical light rail system in the nation in terms of money taken away from city residents to built it.

This long standing FTA safety valve was thrown out. It was replaced with Livability.

Problem is there is no definition of Livability. Car haters may define it as taking cars out of the street. One can hate cars all he wants, but inside them there are human beings. Take cars away and the corresponding activity is largely taken away. Simple math. Greater automobility equals greater prosperity and a better life style.

With "livability" instead of building affordable roads or adding lanes in proportion to population (these lanes will be occupied by low to no emissions vehicles in 20 years) we proposed to build rigid, expensive neighborhood dividers such as elevated rail.

Livability is very similar to Beauty. As in "beauty is in the eye of the beholder. " Some Honolulu residents view the elevated rail as a necessary alternative and a technological asset. Most view it as unnecessary, ugly and largely useless.

Rail systems do little for "livability" and similar vague "smart growth" metrics. What rail systems do is waste money and serve far fewer people that they were planned for. Latest example, is the Sounder light rail in Seattle. Emory Bundy estimates that "as of 2008, $1,430,000,000 capital cost for Sounder, 2.22 times the price proffered in 1996 ($647,000,000 YOE$), a cost overrun of $783 million, 122%."

But that's the good news. The actual ridership story is fantasy versus reality: Numbers out of mouths of politicians ans their hired "experts" versus the number of people actually using the rail systems. Let's follow their history from fantasy to reality. Note that their system took 13 years to materialize so the 1996 local politicians are now at a law firm, Congress or prison, fully unaccountable for this boondoggle.

The 1996 Sound Move Plan promised at least 105,000 Central Link light rail daily (one-way) trips in 2010.

By late 2001, with light rail trimmed-back to Airport/Initial Segment, the target was lowered to 45,000 daily boardings by 2020.

In 2008, with Airport Link nearing completion, Sound Transit's 2010 target was lowered to 32,600.

In 2009, as opening day for Airport/Initial Segment approached, the target for 2010 was reduced again, to 26,000.

In 2009 roughly 15,000 daily trips are being recorded.

So in 2010 the expectation is that actual daily riders would be less than half those promised in late 2001 and less than a quarter those promised in 1996.

Evidence like this does not phase Hannemann, Caldwell, Apo, Carlisle and the (mostly paid in cash, in jobs or in kind) Go-Rail-Go rail advocates.

Good thing Governor Lingle promises to take a hard look into the Final EIS and the numbers and proposed mitigation plans in it. By all accounts the public is on her side. Here is a sample from Pacific Business News: 64% believe that the governor is asking important questions.





Wednesday, January 20, 2010

Mufi's Rail: Scrap the Whole Thing

A couple of local TV stations posted online polls after covering the presentation by the Hawaii Chapter of the American Institute of Architects at the Capitol hosted by Governor Lingle on January 18, 2010.

A fairly comprehensive and neutrally worded poll was developed by the FOX affiliate KHON as part of their well-watched Channel 2 News.
The poll asked "How should the City and State proceed with the rail transit project?" and gave four options [my comments in brackets]

(1)
Elevated as planned [this is the city's proposal or Mufi's Rail]

(2)
At ground level [this is the vaguely described option supported by the Hawaii Chapter of the American Planning Association]

(3)
Mix of above and at ground level [a specific design has been presented by rail expert Phil Craig funded by Bishop Estate and supported by American Institute of Architects-Hawaii]

(4)
Scrap the whole thing [this is the Panos and Stop Rail Now preferred option]

Conclusion? Basically two thirds opined that the whole thing should be scrapped!

Below I show a snapshot of the poll at 10:30 AM the next day with numbers only slightly changed from those reported by Joe Moore at the 10 PM news. [Polls unpopular to the establishment tend to disappear quickly.]

There is wisdom into not rushing mega-projects but contemplating them carefully. It took about four years but the public now gets it: The proposed rail is a boondoggle that we don't need and we can't afford.
Will elected officials get it soon enough?

Monday, January 18, 2010

State of the Rail? Stuck!

The panel presentations of the Hawaii Chapter of the American Institute of Architects hosted by Hawaii governor Linda Lingle on January 18, 2010 revealed many of the weaknesses of the city's proposed rail plan. Here is a sample:

  1. The city is stuck with its environmental compliance and cannot issue a final Environmental Impact Statement (EIS.)
  2. The city's EIS is too deficient to withstand scrutiny at courts.
  3. The city's EIS failed to study a true light rail system. (Note that the voters in 2008 were told that the city was proposing a light rail system.)
  4. Even if the governor wanted to sign an environmental approval, there is no document for her to sign.
  5. There is no federal environmental approval.
  6. There is no federal approval of any funding in any amount.

The governor's panel was a good example of open process as apposed to Mufi Hannemann's lectures and the Parsons Brinkerhoff's smoke and mirrors shows.

There were several references to the Alternatives Analysis, so I spent a little time reviewing this November 2006 document for which two past Hawaii Department of Transportation directors voted in approval (Hirata and Hayashida).

On page 5-2 the Alternatives Analysis says that the East Kapolei to Ala Moana cost would be 3.6 billion dollars, and the full project from West Kapolei to UH and Waikiki would be 5.5 billion dollars. In late 2009 Mufi Hannemann gloated that construction costs have dropped and that Honolulu will get a bargain for building the proposed rail. Really? Why is today's cost for the East Kapolei to Ala Moana system 5.3 billion or 47% higher than the cost estimated in 2006?

Table 5-9 of the Alternatives Analysis projected that in 2009 249 million dollars would have been spent for rail construction. Yet no construction has taken place and this has nothing to do with rail lawsuits or state administration approvals. Simply the city promises big and delivers small.

The governor is correct is pointing out that 2010 is not 2006. Money is a huge issue now at all levels. (It is not an exaggeration to say that now the U.S. builds projects by borrowing money from Asia.)

The proposed rail that is on the table now is dangerously unaffordable and it will undermine the overall ability of the state to deliver other vital projects. This is clearly shown by a desperation act of the city in the latest version of the rail budget. In order to balance the proposed rail budget, it stole $330 million from TheBus budget. This is before any real construction cost overruns have taken place.

Honolulu must not forget San Juan's experience where costs projected by the same consultant actually doubled.

AIA-Hawaii panelists insisted that for this transit project to succeed it must serve the UH-Manoa campus and Waikiki. In this case, the cost of the project is about 8 billion dollars, and, if San Juan experience is repeated, the actual cost could be 16 billion dollars. At this rate, no other project can be built in Hawaii for 20 years. No sewers, no water lines, no roads, no new schools, airport buildings or harbor piers.

The elevated rail system proposal is economic suicide for current residents and their children.

Now some think that solving the congestion problem is worth this risk. Unfortunately nowhere has a rail line solved any traffic congestion problem. The city's numbers clearly show this. At the present time TheBus carries 7 out of 100 trips on Oahu. With TheBus and TheRail combined in 2030 this will explode to ... 8 out of 100 trips. Sorry, over 90% of the trips will be stuck in traffic!

Unfortunately the news is even worse for those who hope that TheRail will reduce road congestion. Both San Juan and Seattle recently opened rail lines and their ridership is only one third of the hoped for level. What does this mean for Honolulu? After paying well over five billion dollars, transit trips will increase from 7 percent to 7.3 percent. More taxes, no relief.

Sunday, January 10, 2010

The Washington Metro

Today Sunday January 10 is my second day in a five day day visit in Washington, D.C. where I attend the 89th annual meeting of the Transportation Research Board, a unit of the National Academy of Engineering.

I decided to introduce Metro to Katie and 15 month old Endie so they can visit the Capital Mall, the Smithsonian and other fine museums while I am at the conference.

You will not believe the state of disrepair of this well-over 10-billion dollar public investment. Our station is more than four stories deep into the ground but the ADA-mandated elevators do not work. People who cannot ride the 3 minute long steep escalator have to wait for buses to take them to other stations.

None of the elevators in the platform of our station were working. They were closed with long messages about "pardon our appearance" followed by specific messages of when the improvements will be completed. Yet there were stickers on the original dates extending the delivery of the fix to February 2010.

On the way back from Metro Center, half of the Red line is single tracked for "scheduled maintenance". Those who go to near destinations have trains every five minutes. Those who go to far destinations have trains every 15 minutes.

It is 28F today in DC and the stations are very cold. Waiting a few minutes with a baby in the cold is very uncomfortable. Waiting at the Kapolei and other leeward stations in the summer will be similarly uncomfortable. And if you pile up the walk, elevator, escalator, ticketing and wait times, plus transfers to buses, the door to door travel time by mass transit is twice the travel time by car. That's what the U.S. Census reports for 2000.

The condition of the Metro is only a small and sad indication that the nation is broke and its transportation is in distress. Having the Metro in such disrepair and at the same time handing out billions to Honolulu for its ridiculous 20 mile train to suburbia is very bad public policy.

In most U.S. urban areas metro rail is too inconvenient, too expensive and too unproductive. The sunny and touristy city of Miami's rail system is an example of all these negative outcomes combined. The single rail line in the 2.2 million population San Juan in Puerto Rico is another example of negative outcomes. Honolulu hopefully won't become the next victim of misguided planning and political ambition.