Wednesday, January 20, 2010

Mufi's Rail: Scrap the Whole Thing

A couple of local TV stations posted online polls after covering the presentation by the Hawaii Chapter of the American Institute of Architects at the Capitol hosted by Governor Lingle on January 18, 2010.

A fairly comprehensive and neutrally worded poll was developed by the FOX affiliate KHON as part of their well-watched Channel 2 News.
The poll asked "How should the City and State proceed with the rail transit project?" and gave four options [my comments in brackets]

(1)
Elevated as planned [this is the city's proposal or Mufi's Rail]

(2)
At ground level [this is the vaguely described option supported by the Hawaii Chapter of the American Planning Association]

(3)
Mix of above and at ground level [a specific design has been presented by rail expert Phil Craig funded by Bishop Estate and supported by American Institute of Architects-Hawaii]

(4)
Scrap the whole thing [this is the Panos and Stop Rail Now preferred option]

Conclusion? Basically two thirds opined that the whole thing should be scrapped!

Below I show a snapshot of the poll at 10:30 AM the next day with numbers only slightly changed from those reported by Joe Moore at the 10 PM news. [Polls unpopular to the establishment tend to disappear quickly.]

There is wisdom into not rushing mega-projects but contemplating them carefully. It took about four years but the public now gets it: The proposed rail is a boondoggle that we don't need and we can't afford.
Will elected officials get it soon enough?

Monday, January 18, 2010

State of the Rail? Stuck!

The panel presentations of the Hawaii Chapter of the American Institute of Architects hosted by Hawaii governor Linda Lingle on January 18, 2010 revealed many of the weaknesses of the city's proposed rail plan. Here is a sample:

  1. The city is stuck with its environmental compliance and cannot issue a final Environmental Impact Statement (EIS.)
  2. The city's EIS is too deficient to withstand scrutiny at courts.
  3. The city's EIS failed to study a true light rail system. (Note that the voters in 2008 were told that the city was proposing a light rail system.)
  4. Even if the governor wanted to sign an environmental approval, there is no document for her to sign.
  5. There is no federal environmental approval.
  6. There is no federal approval of any funding in any amount.

The governor's panel was a good example of open process as apposed to Mufi Hannemann's lectures and the Parsons Brinkerhoff's smoke and mirrors shows.

There were several references to the Alternatives Analysis, so I spent a little time reviewing this November 2006 document for which two past Hawaii Department of Transportation directors voted in approval (Hirata and Hayashida).

On page 5-2 the Alternatives Analysis says that the East Kapolei to Ala Moana cost would be 3.6 billion dollars, and the full project from West Kapolei to UH and Waikiki would be 5.5 billion dollars. In late 2009 Mufi Hannemann gloated that construction costs have dropped and that Honolulu will get a bargain for building the proposed rail. Really? Why is today's cost for the East Kapolei to Ala Moana system 5.3 billion or 47% higher than the cost estimated in 2006?

Table 5-9 of the Alternatives Analysis projected that in 2009 249 million dollars would have been spent for rail construction. Yet no construction has taken place and this has nothing to do with rail lawsuits or state administration approvals. Simply the city promises big and delivers small.

The governor is correct is pointing out that 2010 is not 2006. Money is a huge issue now at all levels. (It is not an exaggeration to say that now the U.S. builds projects by borrowing money from Asia.)

The proposed rail that is on the table now is dangerously unaffordable and it will undermine the overall ability of the state to deliver other vital projects. This is clearly shown by a desperation act of the city in the latest version of the rail budget. In order to balance the proposed rail budget, it stole $330 million from TheBus budget. This is before any real construction cost overruns have taken place.

Honolulu must not forget San Juan's experience where costs projected by the same consultant actually doubled.

AIA-Hawaii panelists insisted that for this transit project to succeed it must serve the UH-Manoa campus and Waikiki. In this case, the cost of the project is about 8 billion dollars, and, if San Juan experience is repeated, the actual cost could be 16 billion dollars. At this rate, no other project can be built in Hawaii for 20 years. No sewers, no water lines, no roads, no new schools, airport buildings or harbor piers.

The elevated rail system proposal is economic suicide for current residents and their children.

Now some think that solving the congestion problem is worth this risk. Unfortunately nowhere has a rail line solved any traffic congestion problem. The city's numbers clearly show this. At the present time TheBus carries 7 out of 100 trips on Oahu. With TheBus and TheRail combined in 2030 this will explode to ... 8 out of 100 trips. Sorry, over 90% of the trips will be stuck in traffic!

Unfortunately the news is even worse for those who hope that TheRail will reduce road congestion. Both San Juan and Seattle recently opened rail lines and their ridership is only one third of the hoped for level. What does this mean for Honolulu? After paying well over five billion dollars, transit trips will increase from 7 percent to 7.3 percent. More taxes, no relief.

Sunday, January 10, 2010

The Washington Metro

Today Sunday January 10 is my second day in a five day day visit in Washington, D.C. where I attend the 89th annual meeting of the Transportation Research Board, a unit of the National Academy of Engineering.

I decided to introduce Metro to Katie and 15 month old Endie so they can visit the Capital Mall, the Smithsonian and other fine museums while I am at the conference.

You will not believe the state of disrepair of this well-over 10-billion dollar public investment. Our station is more than four stories deep into the ground but the ADA-mandated elevators do not work. People who cannot ride the 3 minute long steep escalator have to wait for buses to take them to other stations.

None of the elevators in the platform of our station were working. They were closed with long messages about "pardon our appearance" followed by specific messages of when the improvements will be completed. Yet there were stickers on the original dates extending the delivery of the fix to February 2010.

On the way back from Metro Center, half of the Red line is single tracked for "scheduled maintenance". Those who go to near destinations have trains every five minutes. Those who go to far destinations have trains every 15 minutes.

It is 28F today in DC and the stations are very cold. Waiting a few minutes with a baby in the cold is very uncomfortable. Waiting at the Kapolei and other leeward stations in the summer will be similarly uncomfortable. And if you pile up the walk, elevator, escalator, ticketing and wait times, plus transfers to buses, the door to door travel time by mass transit is twice the travel time by car. That's what the U.S. Census reports for 2000.

The condition of the Metro is only a small and sad indication that the nation is broke and its transportation is in distress. Having the Metro in such disrepair and at the same time handing out billions to Honolulu for its ridiculous 20 mile train to suburbia is very bad public policy.

In most U.S. urban areas metro rail is too inconvenient, too expensive and too unproductive. The sunny and touristy city of Miami's rail system is an example of all these negative outcomes combined. The single rail line in the 2.2 million population San Juan in Puerto Rico is another example of negative outcomes. Honolulu hopefully won't become the next victim of misguided planning and political ambition.

Thursday, December 3, 2009

Revitalize Honolulu with BRT

The news from Cleveland is that in October 2008, construction finally ended along one of major avenues. "The crumbling Euclid Avenue corridor had become a sparkling link between downtown and University Circle. The sleek buses, the slick stations and the smooth road offered a potential path to urban renewal." (1)

What spurred this renewal? A bus rapid transit, or BRT system. The same can be applied for a connection between the UH-Manoa and Honolulu's downtown. We proposed this back in 2002 (2), but the city's planners preferred to take lanes away from Kapiolani Boulevard, at a loss of two lanes along the contraflow peak direction. That BRT proposal ended when the FTA revoked its initial approval of the Harris administration proposal.

Note that King Street and Beretania Streets have the most schools, doctors offices, markets, and other small businesses per mile of arterial street in Honolulu. A BRT system will be vastly more useful (and affordable) than any rail system with mile apart stations.

If Honolulu was not drowning in its multi-billion rail system then it would be applying for these ready-to-use Federal Transit Administration special funds for BRT:

U.S. Transportation Secretary Ray LaHood today announced that FTA will publish a solicitation for grant applications for streetcar and bus circulators and bus facilities. The $280M in grants will be awarded in conjunction with the DOT-HUD-EPA Livability Initiative. For the urban circulator projects, a maximum amount of $25M per project will be made available. (3)

This is one of many indications that change in City Hall is the only hope for refocusing Honolulu projects on cost-effective congestion solutions and essential infrastructure fixes.


(1) http://www.cleveland.com/business/index.ssf/2009/11/clevelands_euclid_corridor_pro.html

(2) http://www.eng.hawaii.edu/~panos/pdp_brt.pdf

(3) http://www.dot.gov/affairs/2009/dot18509.htm